Retention Trusts for Lower Tier Subcontracts
Retention Trusts for Lower Tier Subcontracts
Under the current phrase of the Statutory Trust Framework, Retention Trusts do not apply to lower tier subcontracts unless:
- the first-tier subcontractor is a related entity of the head contractor; or
- the regulation prescribes that the first-tier subcontract is a Project Trust Contract.
In either of those cases, the second tier subcontract cash retentions must be held in a Retention Trust Contract for which the first tier subcontractor is the trustee.
In the final phase of the Statutory Trust Framework, Retention Trusts are required for all lower tier subcontracts if:
- the head contract is a Project Trust Contract; and
- subcontractors at any tier hold cash retention on a lower tier subcontractors.
A Retention Trust for a lower tier subcontract has the same requirements as a Retention Trust for a subcontract, details of which can be found here.